The project for the Bronte 6th Form accommodation at Casterton School was a complete refurbishment of the existing plumbing & heating systems.
The requirements were :
- Phase 1: Complete plumbing & heating of top floor accommodation with 12 en-suite bathrooms.
- Phase 2: Complete plumbing & heating of middle floor accommodation with 12 en suite bathrooms.
In 2010 Casterton School contracted Wheildon’s to install all of the plumbing and heating on a split two-year project to refurbish and update Bronte House, a three storey eighteen hundreds building.